Projects: Maritime
Cape Jervis & Penneshaw Berthing Structures, Holding Measures Options: DPTI
Options for restoration and improvement to structures at Cape Jervis and Penneshaw that have seen degradation and damage from berthing ferries.
CAPEX: Confidential | DATES: 2019 | LOCATION: Kangaroo Island, SA
OUR INVOLVEMENT
Capisce QS have provided option estimates for remediation/restoration and improvement works to berths. Option works include timber rubbing chafers, steelwork to mooring structures, replacing steel with concrete structures and pile work.
VALUE ADDED
Capisce QS specialist industry experience and knowledge using previous project rates, market information and best practice of our profession to produce estimates that represent true market costs have enabled DPTI to proceed with confidence in their procurement process.
Lincoln Cove Marina Replacement and Maintenance of Assets: DPTI
Replacement and ongoing maintenance of assets including revetments, sheet-pile walls, timber promenades, pavements and boat ramps; work divided into different timeframes (0-5 years, 5-10 years and 10-20 years).
CAPEX: Confidential | DATES: 2020 | LOCATION: Port Lincoln, SA
OUR INVOLVEMENT
Capisce QS provided estimates of replacement and on-going maintenance costs for assets within the Lincoln Cove Marina, with responsibilities allocated to the local council and DPTI.
VALUE ADDED
Capisce QS’s specialist industry experience and knowledge using previous project rates and best practice to produce the estimates, provided DPTI with the basis and confidence when making procurement and budgetary decisions.
Berth 6 & 7 Bollards and Fenders Upgrade: Flinders Ports
The Berth 6 and Berth 7 upgrading works included construction of additional row of fenders right below the existing fenders with new supporting frames, chains and fixings to concrete; addition of 8 off 150T double bitt bollard with fixing bolts; and refurbishment and relocation of 20 off existing double bitt bollards with new fixing bolts. The Landside upgrading works included demolition of existing mooring dolphin and gangway; construction of 2 off new landside bollard structures with piles, pile caps, 150T bollards and capstans; concrete/grout fill voids between armor rock to create a smooth surface to prevent mooring lines catching; construction of 1 off new access gangway supported by monopile with access ladder and fendering.
CAPEX: AUD 6.4M | DATES: 2021 | LOCATION: Port Adelaide, SA
OUR INVOLVEMENT
Capisce QS was engaged by Flinders Ports to provide cost estimation for berth 20 upgrades.
VALUE ADDED
Capisce QS’ specialist industry experience and knowledge using previous project rates, market information and experience with the client, allows for cost advice that enables Flinders Ports to proceed with confidence in their procurement process.
Give us a call to talk to our team to hear how we added value on all noted projects
Project Title | Date |
---|---|
Berth 20 Construction | 2019 |
Thevenard Hopper Project | 2019 |
Berth 25 Equinor Asset Valuation | 2020 |
Berth 18-20 Concrete Remediation Works | 2020 |
Pt Lincoln Water Main Replacement Berth 7 & 9 | 2020 |
FACT Berth 6&7 Bollards and Fenders Upgrade | 2020 |
Channel Widening Audit Costings | 2020 |
IH Berth 20 & Northern Wingwall Remediation | 2020 |
Klein Point Jetty Refurbishment Pricing | 2020 |
H Berth Southern Sheet Pile Wall Upgrade | 2020 |
Kangaroo Island Ports Interim and Integrated Works | 2020 |
Thevenard Navigation Aids and Jetty Remediation | 2020 |
Fact Berth 6&7 Bollards and Fenders Upgrade Rev 1 | 2020 |
Coffin Bay Jetty Refurbishment | 2021 |
Steel Assets Condition Assessment Repairs and Replacement Costs | 2021 |
Electrical Lighting Upgrade Design Phase | 2021 |
ADM Power Outlets Port Pirie Berth 5 | 2021 |
O'Sullivans Beach and Anxious Bay Boat Ramp Projects | 2021 |
Kangaroo Island Ports - Inner and Outer Structures | 2021 |
Port Pirie New Amenities Building | 2021 |
Port Germein Jetty Refurbishment | 2021 |
Passenger Terminal Brickwork | 2021 |
FACT Shed Pavement Rehabilitation | 2021 |
OH3 100t Hardstand | 2022 |
Berths 4-10 Electrical Lighting Upgrade | 2022 |
Outer Harbour 2 and 4 Electrical Lighting Upgrades | 2022 |
Anxious Bay Boat Ramp Options. | 2022 |
Cape Jervis Penneshaw Berthing Structures | 2019 |
Lincoln Cove Marina | 2020 |
West Beach Boat Ramp Replacement | 2021 |